It also starts at 0, has steps on days 2, 4, 5 and 6, and ends at 26, so its course up to day 9 is the same as イ; however, the last step (+4, the cost of C) is placed on day 8. C takes 4 days after B (which finishes on day 5), so it is completed on day 9 and cannot be recorded on day 8. The step is one day too early, which makes this graph wrong.
○イ
正解The cost of each activity is recorded at the time it is completed, so first find the completion day of each activity from the preceding-activity constraints. A has no preceding activity, so it starts on day 0 and finishes on day 2. Once A is finished, B, D and F can all start: F takes 2 days and finishes on day 4, B takes 3 days and finishes on day 5, and D takes 4 days and finishes on day 6. C starts after B finishes (day 5), takes 4 days and finishes on day 9. E starts after D finishes (day 6), takes 5 days and finishes on day 11; G can start only on day 6, when both D and F are finished, takes 6 days and finishes on day 12. Therefore only five activities — A, F, B, D and C — are completed by day 10, and the cumulative cost rises to 5 on day 2, 10 on day 4 (+5), 17 on day 5 (+7), 22 on day 6 (+5) and 26 on day 9 (+4); because E and G are not yet finished, it is still 26 on day 10. The graph starts at 0, has steps on days 2, 4, 5, 6 and 9, and stays flat at 26 from day 9 onward — only graph イ has this shape.
×Incorrectウ
A cost of 5 is already recorded at day 0, which means the cost of A is recorded at its start instead of at its completion (day 2). In addition, the steps fall on days 2, 3, 4, 6 and 9, all shifted earlier, and the cumulative cost on day 10 is about 32, a value that already includes the costs of E and G. On day 10, E (finished on day 11) and G (finished on day 12) are not yet complete, so the total cannot reach that amount.
×Incorrectエ
As in ウ, recording the cost of A on day 0 is wrong, and the steps fall on days 2, 3, 4, 7 and 9, which do not match the actual completion days (2, 4, 5, 6 and 9). The cumulative cost on day 10 is also about 32, an excessive value that includes the costs of E and G even though they are not yet finished.
ここがポイント
Use the specified preceding activities to trace, one by one, the earliest start day and the completion day of each activity. An activity that has several preceding activities (G and H in this question) cannot start until all of them are finished, that is, until the latest of their completion days.
Following the condition that the cost is recorded when each activity is completed, each cost appears as a single step on that activity's completion day. When narrowing down the choices with a cumulative cost graph, check both the position of each step (the completion day) and its height (the cost of that activity).