With only 1 additional person, the total becomes 11 people advancing 11% per month, which is only 55% over 5 months. 40+55=95%, which does not reach 100% and misses the deadline, so it is insufficient.
○イ
正解First, find the “productivity from April onward” from the actual results. The actuals are 20% at end of March → 30% at end of April → 40% at end of May, meaning 10 people advance 10% each month. So productivity is 1% per person per month. Next, look at the remaining work: 40% is done at end of May, so 100−40=60% remains. The deadline is end of October, leaving 5 months: June, July, August, September, and October. To strictly meet the deadline, progress must be 60÷5=12% each month. With only the existing 10 people, only 10% is made each month, which is 2% short. Additional people also contribute 1% per person per month, so covering the 2% gap requires at least 2 additional people. Therefore the correct answer is イ (2 people).
×Incorrectウ
5 is the number of months in the remaining period (5 months from June to October), not the number of additional people needed. Adding 5 people would advance 15% per month and 75% over 5 months, which is greatly excessive and does not satisfy the condition of the minimum number of people.
×Incorrectエ
12 is the total number of people needed to advance 12% per month (12%÷1%=12 people), not the additional people the question asks about. After subtracting the existing 10 people, 12−10=2 people is the additional amount. This is a wrong answer that confuses the total number with the additional number.
ここがポイント
A quantitative progress-management approach: derive per-person monthly progress (productivity) from the actual results, compute the required monthly progress rate as remaining work ÷ remaining period, and convert the shortfall into additional people.
Distinguish the additional people the question asks about from the total people needed (total 12 − existing 10 = 2 additional).