Skip to content

平成30年度 秋期 ITパスポート試験 問36

This question's explanation and your answers so far.

問36
頻出度★★★

プロジェクトにおけるスコープの変更に該当するものとして, 最も適切なものはどれか。

出典 平成30年度 秋期 ITパスポート試験 問36
解説

問 36

  • Incorrectア

    Changing the development location is merely a change to the environment and resources in which the work is done. The range of work to be performed and its deliverables does not change, so it is not a change in scope.

  • Incorrectイ

    Adding development members is a change to human resources (personnel), which falls under Project Resource Management. The range of work being undertaken does not itself increase, so it is not a change in scope.

  • Incorrectウ

    Changing the outsourcing contractor is a change to who undertakes that work (the procurement source). The range of the work content and deliverables stays the same, so it is not a change in scope.

  • エ

    正解 Scope refers to the range of work a project must perform and its deliverables. Option エ adds a new task, “support for the operational testing performed by the customer,” to the project's work, which expands the very range of work the project must do. This is a change to what Project Scope Management controls, so it corresponds to a change in scope.

ここがポイント
  • Scope is the range of work the project must perform and its deliverables; adding to, removing from, or altering it constitutes a change in scope.
  • Changes to resources or procurement sources — such as location, personnel, or the outsourcing contractor — do not change the range of work performed, so they are not changes in scope.
用語

Your answers