5,000 units misreads the condition that the order placed on the first business day of May is used for production “from the following month onward (= June).” It instead treats the order as covering the shortfall of May’s 6,000-unit production and subtracts the carried-over 1,000 units (6,000−1,000). What actually needs to be covered is June’s 7,000-unit production; this answer mistakenly shifts the corresponding month one step earlier.
○イ
正解Because Part B is “delivered at the end of the current month and used in production from the following month onward,” the stock available for a given month’s production is the previous month-end stock. Tracing the stock changes: the 6,000 units in stock at the end of March are consumed by April production (5,000 units), leaving 1,000 units. The 6,000 units ordered on the first business day of April are delivered at the end of April, so the end-of-April stock is 1,000+6,000=7,000 units. Next, consuming them in May production (6,000 units) leaves 1,000 units. Let the quantity ordered on the first business day of May be X units; this batch is delivered at the end of May and is used for June production, so the end-of-May stock is 1,000+X units. June production requires 7,000 units, so the stock available for June production (= end-of-May stock) only needs to reach 7,000 units or more. This gives 1,000+X≥7,000, i.e., X≥6,000. The minimum order quantity is 6,000 units, and the correct answer is イ.
×Incorrectウ
7,000 units takes June’s production quantity of 7,000 units directly as the order quantity, but forgets to subtract the 1,000 units of stock carried over at the end of May (the remainder after subtracting May’s 6,000-unit production from the 7,000 units at the end of April). Taking the carry-over into account, the required order is 6,000 units.
×Incorrectエ
8,000 units adds the 1,000 units of carried-over stock—which should have been subtracted—to June’s production quantity of 7,000 units instead (7,000+1,000), or overestimates the stock changes. Since the carried-over 1,000 units can be used, ordering 6,000 units is enough.
ここがポイント
Stock-change calculation: end-of-month stock = previous month-end stock − current-month consumption (= current month’s production quantity) + current-month delivery quantity. Fill in the blank cells of the table month by month and work backward to find the required order quantity.
Procurement lead-time offset: because Part B is “delivered at month-end and used from the following month onward,” the stock available for a given month’s production is the previous month-end stock. The key is to match this up correctly: the order on the first business day of May covers June production.