平成25年度 春期 ITパスポート試験 問7

This question's explanation and your answers so far.

問7
頻出度★★☆

ある部品の生産ラインは二つの工程 A,B の順で構成されており,各工程の機械台数,部品 1 個の生産に要する作業時間,不良率は表のとおりである。1 日の稼働時間を 10 時間とするとき,この生産ラインの 1 日の生産能力(良品が生産される数)は何個か。ここで,工程 A での不良品は工程 B には送らないものとする。また,機械の故障時間や段取り時間,工程間の仕掛品在庫は考えないものとし,仕掛中のものは終了時間が来ても最後まで仕上げるものとする。

工程機械台数作業時間/個不良率
A1 台3 分5%
B1 台2 分10%
出典 平成25年度 春期 ITパスポート試験 問7
解説

問 7

  • ア

    正解 The correct answer is ア “171”. Work through the calculation step by step. First, convert the daily operating time of 10 hours into minutes: 10×60 = 600 minutes. Process A has 1 machine and takes 3 minutes per unit, so in one day it can handle 600÷3 = 200 units. However, the defect rate of process A is 5%, and the question states that “defective products from process A are not sent to process B,” so only the good units, 200×(1−0.05) = 190, are passed on to process B. Next, look at process B: 1 machine takes 2 minutes per unit, so in 600 minutes it can handle up to 600÷2 = 300 units. In other words, B’s capacity of 300 units is larger than the 190 units that actually arrive, so B is not the constraint (bottleneck), and all 190 units are processed by B (190×2 = 380 minutes is enough, and the question says that a part being worked on is finished to completion even if the end time has passed). Finally, subtracting the 10% defect rate of process B, the final number of good units is 190×(1−0.10) = 171. Therefore the daily production capacity of this line is 171 units, and ア is correct. There are two key points: the process with the smaller capacity, process A (3 min/unit), determines the flow of the whole line; and the defect rates must be applied in two stages, A and B, multiplied in turn.

  • Incorrectイ

    180 units comes from 200×(1−0.10) = 180, that is, applying only the 10% defect rate of process B to process A’s output of 200 units while overlooking the 5% defect rate of process A. In this question, 5% defects also occur at process A, so by the time the units reach B the count has already dropped from 200 to 190. Defects occur at each process, so both A’s 5% and B’s 10% must be multiplied in turn (200×0.95×0.9 = 171). This is a wrong answer that misses the point that when processes are connected in series, the yield is the product of the good-unit rates of the individual processes.

  • Incorrectウ

    200 units comes from 600÷3 = 200, which is simply the number of units process A can take in and work on in one day, with no defect rate taken into account at all. What the question asks for is “the number of non-defective units produced,” so A’s 5% defects and B’s 10% defects must be subtracted. 200 units is nothing more than the processing capacity of process A (output measured on an input basis); it is not the number of good units that come out at the end of the line.

  • Incorrectエ

    257 units comes from taking 600÷2 = 300 units as the starting point and computing 300×0.95×0.9 = 256.5 ≈ 257; it is a wrong answer that mistakes which process is the bottleneck. Process B, at 2 minutes per unit, is indeed faster, but only parts that have passed through A flow into B, so what determines the flow of the whole line is the slower side, namely process A, which takes 3 minutes per unit. The production capacity of processes in series is determined by the process with the smallest capacity (the bottleneck), and the capacity of a fast process cannot be treated as the capacity of the whole line.

ここがポイント
  • The production capacity of a line made up of processes connected in series is determined by the process with the smallest processing capacity (the bottleneck). The number of units processed per machine is found as “operating time ÷ work time per unit × number of machines”; in this question process A gives 600÷3 = 200 units/day and process B gives 600÷2 = 300 units/day, so the slower process A determines the flow of the line. Do not mistake the capacity of the faster process for the capacity of the whole line.
  • The number of good units (the yield) is found by multiplying the good-unit rates of each process together in turn. If process A with a 5% defect rate and process B with a 10% defect rate are in series, the final number of good units is input × (1−0.05) × (1−0.10); it is neither a matter of adding the defect rates and subtracting 15%, nor of subtracting only one of them. Also keep in mind that in this question, because A’s defective units are not sent to B, B’s load drops to 190 units.