平成30年度 春期 ITパスポート試験 問43

This question's explanation and your answers so far.

問43
頻出度★★★

システム開発を示した図のアローダイアグラムにおいて,工程 A と D が合わせて 3 日遅れると,全体では何日遅れるか。 図のアローダイアグラム(凡例: 円が結合点,矢線上が「工程名」,矢線下が「所要日数」): - 開始結合点から 3 本の矢線が出て,それぞれ別の経路を通り,最後に同じ終了結合点に集まる。 - 経路1(上): 開始 →[工程 A,所要日数 2]→ 結合点 →[工程 D,所要日数 4]→ 終了 - 経路2(中): 開始 →[工程 B,所要日数 4]→ 結合点 →[工程 E,所要日数 3]→ 終了 - 経路3(下): 開始 →[工程 C,所要日数 7]→ 結合点 →[工程 F,所要日数 1]→ 終了

出典 平成30年度 春期 ITパスポート試験 問43
解説

問 43

  • ア

    正解 In an arrow diagram, the longest path from start to end (the critical path) determines the total duration of the whole project. The durations of the three paths in the figure are A→D = 2 + 4 = 6 days, B→E = 4 + 3 = 7 days, and C→F = 7 + 1 = 8 days. So the original total duration is the critical path C→F, which is 8 days. When processes A and D are delayed by a total of 3 days, the A→D path becomes 6 + 3 = 9 days. The new total duration is the maximum of the three paths = max(9, 7, 8) = 9 days. Therefore the delay is 9 − 8 = 1 day, and the correct answer is “1” (ア).

  • Incorrectイ

    “2” is wrong. This answer mistakes the baseline: it subtracts the second-longest path B→E (7 days) from the delayed A→D path (9 days) to get 9 − 7 = 2. The baseline for the overall delay should be the original critical path C→F at 8 days, so 9 − 8 = 1 day is correct.

  • Incorrectウ

    “3” is wrong. This simply treats the delay of 3 days as the overall delay. The A→D path was originally 6 days, giving it 2 days of slack (float) against the 8-day critical path. Of the 3-day delay, 2 days are absorbed by the slack, so only 1 day propagates to the whole project.

  • Incorrectエ

    “4” is wrong. This misreads “a total of 3 days” as A and D each being delayed by 3 days (6 days in total), making the A→D path 6 + 6 = 12 days and giving 12 − 8 = 4. The question states 3 days in total for A and D combined, so the A→D path only reaches 9 days.

ここがポイント
  • In an arrow diagram, the longest path (the critical path) determines the total duration. In the figure, C→F at 8 days is the critical path.
  • A delay on a non-critical path propagates to the whole project only by the amount by which its delayed length exceeds the critical path. Only what remains after the original slack (float) is used up becomes the overall delay.
用語