Goals of this unit

  • Explain how configuration management keeps the records of configuration items accurate, so they can be relied on when handling changes and failures.
  • Tell change management, which decides whether a change goes ahead, from release and deployment management, which delivers approved changes to the live environment.
  • Explain how service transition proceeds and how it relates to the service acceptance criteria used to decide whether a service may go into use.
Terms at a glance (5)
TermIn one lineQuestion it answersMain records and outputs
構成管理The process that keeps information on the configuration items making up a service accurate and up to dateWhat is the current state?Records of configuration items
変更管理The process that assesses the impact of change requests, decides whether to carry them out, and controls approved changesMay we change it?Records of change requests and approvals
リリース及び展開管理The process that bundles and builds approved changes, tests them, and then deploys them to the live environmentHow do we deliver it to production?Releases (bundles of changes)
サービスの移行Planning and carrying out the move of a new or changed service into live operationHow do we put it into operation?Transition plan
サービス受入れ基準Pass conditions set in advance to judge whether a service may start being used in productionMay we start using it?List of pass conditions

Terms

構成管理Configuration Management

Open in glossary 構成管理

Configuration management (構成管理) is the process of identifying the configuration items that make up a service, such as equipment, software and procedure manuals, and keeping their information accurate and up to date.

Field recordedExample entry
Item nameOrder-processing server No. 2
VersionOrder application version 3.4
Location and ownerData center 2, operations team B
Links to other itemsLinked to the inventory database

A configuration item is each individual part of a service registered as something to be managed, with its version, location and links to other items recorded. These records are gathered in the configuration management database (CMDB) and serve as the reference when checking the impact of a change or tracing the cause of a failure.

AnalogyIt is like a library catalog. Only when it correctly shows which books sit on which shelf, and how many copies there are, can you plan replacements or repairs.

How to rememberThe Japanese name 構成管理 literally means "composition management": it writes down how the parts are put together. Configuration carries the same sense of an arrangement of parts.

Exam points

  • ExamThe process of keeping a complete picture of an organization's IT assets (IT資産) and continuing to manage them in a register or database is configuration management (構成管理).
  • ExamWhether the management of IT assets recorded by configuration management is working well can be measured by, for example, the number of software licenses (ソフトウェアライセンス) left unused.

3 past questions on this term 構成管理

変更管理Change Management

Open in glossary 変更管理

Change management (変更管理) is the process that takes in change requests for a service, assesses their impact and risk, decides whether they may go ahead, and controls approved changes so they proceed as planned.

  1. Receive the change request
  2. Assess impact and risk
  3. Decide to approve or reject
  4. Plan the work and hand over

Plan the steps for the approved change and pass building and deployment to release and deployment management.

4 / 4

A change request (RFC) is a recorded proposal to modify a service, such as adding a feature, fixing a defect or revising a setting. Change management checks how far the impact reaches using configuration management's records before deciding, and also sets the priority of the work.

AnalogyIt is like a condo board reviewing renovation work. It takes a resident's request, looks at the effect on the whole building before giving permission, and then schedules the work.

How to rememberThe entry document, RFC, stands for Request for Change: the request every change starts from.

Exam points

  • ExamAssessing a change's impact on the service before it is carried out is part of change management (変更管理).
  • ExamChange management does not end at approval: it arranges when and in what order each approved change is carried out, and manages the work so it proceeds as arranged.

3 past questions on this term 変更管理

Configuration Management vs. Change Management

AspectConfiguration ManagementChange Management
Key differenceWhat it handlesRecords configuration item information accurately and keeps it currentAssesses change requests, decides whether they go ahead, and controls the work
What it deals withExisting assets and configurationChanges still to be made
Main recordsConfiguration management database (CMDB)Records of change requests and approvals

リリース及び展開管理Release and Deployment Management

Open in glossary リリース及び展開管理

Release and deployment management (リリース及び展開管理) is the process that bundles changes approved by change management into a release, builds and tests it, and then deploys it to the live environment.

  1. Plan the release
  2. Build and test
  3. Deploy to production
  4. Check after deployment

Confirm it runs without problems in production and record the results.

4 / 4

A release is a bundle of changes packaged together and sent to production, and can include a new software version or equipment being added. Deployment means actually distributing that release to the environment where it is used and putting it into operation. A patch file that fixes a defect is one example of a change that goes into a release.

AnalogyIt is like a moving company. It packs and carries your things, sets up the furniture in the new home so it is ready to use, and arranges in advance how to take items back if they cannot be moved in.

How to rememberRelease means "letting go," and deployment means "spreading out." Picture it as two verbs: let go of what you finished in-house, then spread it out to where the users are.

Exam points

  • ExamPutting approved changes into the live environment is the role of release and deployment management (リリース及び展開管理).
  • ExamNot only software: installing added equipment into the production system and starting to use it also falls within release and deployment management.
  • ExamWhen planning a release (リリース), you anticipate the case where the work does not finish on schedule and decide beforehand how to respond.

3 past questions on this term リリース及び展開管理

Change Management vs. Release and Deployment Management

AspectChange ManagementRelease and Deployment Management
Key differenceRoleDecides whether a change may go ahead, plans the approved change and tracks its progressBuilds and tests approved changes and deploys them to production
ExampleReviewing whether to add a new featureTesting and distributing the version that includes the new feature

サービスの移行Service Transition

Open in glossary サービスの移行

Service transition (サービスの移行) is the planning and carrying out of moving a new or changed service from the development or test environment into live operation.

  1. Plan the transition
  2. Acceptance decision
  3. Go live and start operation

Put the service that meets the criteria into production and hand it over to the operations staff.

3 / 3

What gets moved includes not just software and equipment but also operating procedures, the staffing of those in charge, and guidance for users. Once the service is in production, responsibility passes from the development side to the operations staff, and day-to-day operation begins.

Exam points

  • ExamSoftware installation (ソフトウェア導入) is the stage of deciding the steps of the work and then putting the finished software into the live environment so that it runs. In the transition flow, it corresponds to the step of putting things into production.
  • Mix-upRelease and deployment management (リリース及び展開管理) delivers individual releases to production, whereas service transition (サービスの移行) covers the whole of planning and carrying out the move of a new or changed service into live operation.

1 past questions on this term サービスの移行

サービス受入れ基準Service Acceptance Criteria

Open in glossary サービス受入れ基準

Service acceptance criteria (サービス受入れ基準) are the pass conditions set in advance to judge whether a new or changed service may start being used in production.

Typical items ask whether the required performance is met, whether testing is finished, and whether the operating procedures are in place with staff ready to handle the service. The criteria are agreed with stakeholders at the planning stage, not just before the transition.

AnalogyIt is like the passing score on a driving test. Because the scoring standard is fixed beforehand, anyone looking at the result reaches the same pass-or-fail decision.

Service Transition vs. Service Acceptance Criteria

AspectService TransitionService Acceptance Criteria
Key differenceNaturePlanning and carrying out the move into live operation (an activity)Pass conditions for deciding whether use may begin (a yardstick)

Key points

  • Configuration management keeps records of configuration items and IT assets current, giving other processes a foundation for their decisions.
  • Change management assesses the impact of change requests, decides whether they go ahead, and manages the steps and progress of approved changes.
  • Release and deployment management builds and tests approved changes, prepares a way to roll back, and then deploys them to production.
  • Service transition is the activity of putting a new or changed service into live operation, and whether it may go into use is judged against the service acceptance criteria agreed in advance.

Check questions

4 past questions from this unit

Start the check questions

All past questions in this topic