Service Maintenance and Continual Improvement

頻出~30 min5 terms15 past questions

Goals of this unit

  • Tell service availability management from service continuity management by the scale of the events each one prepares for.
  • Explain how the results shown in service reporting become leads for continual improvement.
  • Decide which of the four PDCA stages a given task belongs to.
Terms at a glance (5)
TermIn one lineRoleMain indicators and outputs
サービス可用性管理Management that keeps a service usable whenever users need it, at the agreed levelKeeping things runningAvailability rate, how rarely failures occur, how fast repairs are made
サービス継続管理Management that prepares to keep a service running, or bring it back, even during major events such as disastersPreparing for emergenciesAlternate sites, recovery targets, continuity plans
サービスの報告The activity of compiling delivery results and goal attainment and sharing them with stakeholdersMaking the situation visibleReports
継続的改善The activity of repeatedly evaluating, finding chances to improve, and acting on themRepeated evaluation and improvementImprovement measures and checks on their effect
PDCAA management approach that repeats four stages: plan, do, check, and actHow improvement moves forwardActions that feed the next plan

Terms

サービス可用性管理Service Availability Management

Open in glossary サービス可用性管理

Service availability management (サービス可用性管理) is the management activity that keeps a service usable whenever users want it, at the agreed level.

Availability is measured with figures such as the availability rate, the share of the committed service hours during which the service could actually be used. The rate goes up as the mean operating time from the end of one repair to the next failure (MTBF) gets longer, and as the mean time from a failure to the end of its repair (MTTR) gets shorter. Availability management keeps watch on these values and, when they look likely to drop below target, takes steps such as adding redundant equipment or revising maintenance.

AnalogyIt is like a bus company that cuts down on breakdowns and keeps spare buses ready to send out at once, so its routes run on schedule.

How to rememberThe Japanese 可用 reads as "fit for use," that is, in a usable state. The English availability likewise means being at hand and ready to use.

Exam points

  • ExamThe aim of availability management is to reach the availability rate (稼働率) agreed as a target. Availability (可用性) is expressed as the share of the agreed service hours during which users could actually use the service.
  • ExamThe availability rate rises both when failures are watched for so they are caught early and when the setup is made redundant so that interruptions become less likely in the first place.
  • ExamAn availability requirement asks that the service be usable whenever needed, apart from planned maintenance hours. Agreements on uptime and the availability rate fall under availability management.

3 past questions on this term サービス可用性管理

サービス継続管理Service Continuity Management

Open in glossary サービス継続管理

Service continuity management (サービス継続管理) is the management activity that prepares a service to keep running, or to be restored within a set time, even when a major event such as a disaster or large-scale failure occurs.

For example, the organization prepares an alternate site and copies of its data, sets a target for how quickly the service must be back, and runs drills and tests to confirm the plan actually works. This work is kept in line with the business continuity plan (BCP) for the business as a whole.

AnalogyIt is like a hospital that installs its own generator in case of a power cut and practices switching over to it several times a year.

How to rememberThe English name is Service Continuity Management. Continuity means carrying on without a break, and it is the same word as the C in BCP.

Exam points

  • ExamService continuity management (サービス継続管理) aims to keep the damage to the business as small as possible when a disaster or similar event strikes. A continuity plan, once drawn up, is also revised according to the results of testing it.

1 past questions on this term サービス継続管理

Service Availability Management vs. Service Continuity Management

AspectService Availability ManagementService Continuity Management
Key differenceWhat it prepares forFailures and interruptions in day-to-day operationMajor events such as disasters or large-scale failures
Main indicatorsAvailability rate, MTBF, MTTRTarget recovery time, alternate sites
Related agreementsAvailability target agreed with usersBusiness continuity plan (BCP) for the whole business

サービスの報告Service Reporting

Open in glossary サービスの報告

Service reporting (サービスの報告) is the activity of recording and compiling a service's delivery results and goal attainment, and sharing them with users and other stakeholders on agreed content and timing.

  1. Measure results
  2. Compile a report
  3. Stakeholders see the same facts
  4. On to improvement planning

Pass the issues the report brings to light on to improvement planning.

4 / 4

A report might include, for instance, a comparison of actual results with the targets agreed with users, and the number and trend of failures that occurred. With a report in hand, users and the provider can talk from the same numbers, and it gives them material for deciding what to improve.

AnalogyIt is like a school report card. Showing grades to the student and family at set times makes it clear what to work on next term.

How to rememberThe English term is service reporting. Report comes from a root meaning "to carry back," and here it means bringing measured results back to the people concerned.

Exam points

  • ExamA service report (サービス報告書) is a document compiled from measured values of the service actually delivered.

2 past questions on this term サービスの報告

継続的改善Continual Improvement

Open in glossary 継続的改善

Continual improvement (継続的改善) is the activity of repeatedly evaluating a service and the mechanisms behind it, finding chances to improve, and carrying them out.

Chances to improve turn up in service reports, monitoring results, and user feedback, among other sources. Candidates are ranked by priority and carried out as planned, and their effect is checked afterward. The work does not end with one fix; what each check shows feeds into the next improvement.

AnalogyIt is like a school sports team that rewatches the video of every practice match and fixes its weak spots one at a time.

How to rememberThe word continual signals that this is not a one-time effort. It suggests repeating at intervals, and it is kept apart from continuous, which means without any break.

Exam points

  • ExamMonitoring (モニタリング) is the activity of continuously watching and recording actual performance on the agreed service level indicators.
  • ExamImproving the service management system (サービスマネジメントシステム) means reviewing the management processes and mechanisms themselves.

2 past questions on this term 継続的改善

PDCA is a management approach that runs through four stages in order, Plan, Do, Check, and Act (corrective action and improvement), and feeds the outcome of Act into the next Plan as the cycle repeats.

  1. Plan: set goals and methods
  2. Do: carry out the plan
  3. Check: measure results against goals
  4. Act: correct based on the gap

In Act, take improvement measures based on the gaps the evaluation found, and carry them into the next Plan.

4 / 4

PDCA is not tied to any one field; it is used in quality management and many other areas. Because the revisions decided in Act are built into the next Plan, goals and methods get a little better with each cycle.

AnalogyIt is like cooking: you settle on a recipe and amounts, cook, taste, and decide to use less salt next time. That decision then goes into the recipe for the next round.

Exam points

  • ExamCheck is the stage where the results of the work are measured and evaluated against target values.
  • ExamAct is the stage where improvement measures are carried out, or plans and goals are revised, in response to the gaps or issues the evaluation found.
  • ExamIn IT service management (IT サービスマネジメント), PDCA serves as the management cycle.

3 past questions on this term PDCA

Continual Improvement vs. PDCA

AspectContinual ImprovementPDCA
Key differenceWhat it isThe goal and activity of continually getting betterA four-stage procedure for carrying it out
What it describesRepeatedly finding and acting on chances to improveThe order of stages: plan, do, check, act

Key points

  • Service availability management aims to meet the agreed availability rate, which rises as MTBF gets longer and MTTR gets shorter.
  • Service continuity management prepares to keep damage to the business small even in a major event, and its continuity plan is tested and revised.
  • Service reporting compiles measured results against targets and gives material for deciding what to improve.
  • In PDCA, measuring results and comparing them with goals is Check, and taking action based on that evaluation is Act.

Check questions

4 past questions from this unit

Start the check questions

All past questions in this topic